Not much to report for this week, but here's the update from our PM:
This week we continued our effort to complete the foundation phase of your home. With the erratic weather it's been a little crazy. We were able to get your homes waterproofing and backfill completed. The underground plumbing has also been completed and we passed our plumbing and slab inspections. I am hoping to pour your interior concrete over the weekend or early next week in preparation for your rough framing package.
No comments:
Post a Comment