Monday, May 16, 2016

Week 13 - Ahhhhhhhhhhhh! I'm so excited!!!!

We received our last update from our project manager on Saturday.  I say last because he likes to save all of his thunder for the pre-settlement walkthrough, which will be happening next Monday!!!!

So the work that was done last week and over the weekend was small, but significant.
  • Trim carpenter came and did his punch outs and corrections
  • Mechanical contractors installed all the finish items (toilets, lights, etc.)
  • Drywall touch ups
  • Carpet installation
  • Stone work.... YESSSS!!!
  • Siding completed over the weekend
  • Shutters, trims and gutters
The Loft 

The Stone



And then this....




  



Next week, we go do our pre-settlement walkthrough on Monday and then we close on Wednesday.  We are "this" close!!!

4 comments:

  1. amazing!!! It looks so fantastic!!

    ReplyDelete
    Replies
    1. Thank you! It looks so much better than I pictured in my head!!

      Delete
  2. Yay!!! So exciting!! We have our walk thru this friday and then close the day after you guys! Can't wait to hear how your walk thru and closing go!

    ReplyDelete
    Replies
    1. Hope everything goes well on your walkthrough! Why is your closing date so far away though?? That would make me crazy!

      Delete